This weekend we have done the ground levelling for the ramp foundation. The location of the ramp was on a slope with about 1m drop from the one side. The space required for the ramp was 9.8m by 13.6m and we levelled +- 1 meter more each side. So we had a lot of ground to move to get it level. This took us from 8am to +- 5pm. The top side we have made a bump/wall to prevent any water running into the ramp location and should stop most of the rain water. We also mixed cement into the ground and used a heavy duty roller to compact the ground to ensure it ‘s not going anywhere. The pictures below shows the before and then final ground level after.
Before: .jpg)
.jpg)